Penn State Great Valley
Malvern, Pennsylvania | Completed July 2016
In the middle of the school year, Trefz Mechanical, Inc. installed a 80 KW 100KVA diesel generator and automatic transfer switch in a challenging remote location with no vehicular access. The project required continued communication and coordination with onsite maintenance crews and other field personnel. A crane was used with coordination at site to keep the area clear of pedestrians. Trefz also constructed a masonry base on a hill on the back of the property. Electrical services to and from the new generator were excavated to the building where electrical piping was continued through a finished interior space which terminated in the electrical room.